Land and data-center sites, North Carolina
Research

Where North Carolina has paused data centers

County and town actions on data centers: moratoriums adopted, ordinances passed, votes pending, and proposals rejected. Every row links to the meeting record or local report.

Last updated 2026.10.03110 rowsDownload the data (CSV)

What the data shows

Local pauses on data centers spread quickly across North Carolina from late 2025 into 2026, mostly as twelve-month moratoriums while boards write zoning standards for the use. Some counties rejected a pause and some adopted an ordinance instead. The county pages and this tracker use the same checked records.

How to use it

Developers can see which jurisdictions have an active pause and which have written standards a project can meet. Reporters and planners can see the pattern by date. Landowners can see whether their county has acted.

How this dataset was built

Rows come from county and town meeting records, agendas, adopted ordinances, and local news reports of the votes. Each row carries a source check dated 2026.10.02. Dates are published only when the opened evidence supports them. A missing date remains blank. Moratoriums that cover only crypto mining are excluded. Actions we could not confirm on a live page are left out until we can.

Questions

Which North Carolina counties have a data center moratorium?

The table lists county, town, and tribal records confirmed in this check, with their current status and any confirmed end date. An end condition can end a pause before its date cap. Proposed actions, expired pauses, permanent bans, and replacement ordinances have separate statuses.

Does a moratorium stop every data center?

No. A moratorium pauses new applications for the period the board sets. Projects already approved usually continue, and courts have exempted individual projects from a later pause.

Can I reuse this data?

Yes. The dataset is licensed CC BY 4.0. Cite FOUND and link to this page.

The data

JurisdictionCountyAdoptedStatusIn effect untilEnd conditionNext eventAreaWhat happenedSources
Alamance CountyAlamance2026.08.17in_effect2027.08.17Unincorporated countyThe county adopted a one-year pause while it studies data-center rules.[48][49]
SpartaAlleghanyproposedProposed one-year pauseThe September 1 agenda lists a public hearing on a one-year data-center moratorium. The hearing outcome remains unconfirmed.[50]
Beaufort CountyBeaufortvote_scheduledProposed one-year term from the effective date, per the draft ordinance in the 2026.10.05 agenda packet2026.10.05: Public hearing and vote on the proposed moratoriumall unincorporated areas of Beaufort County (proposed)The county proposed a one-year pause on data-center development applications in its unincorporated areas. The hearing and vote are on the 2026.10.05 agenda, with the draft ordinance in the packet.[14][51]
ElizabethtownBladenproposedProposed one-year pauseTown limits and ETJThe town proposed a one-year pause on data-center development approvals and advertised a June 15 hearing. Its outcome remains unconfirmed.[52][53]
Boiling Spring LakesBrunswick2026.06.02in_effect2027.06.02Earlier approval of new data-center zoning regulationsCity planning jurisdictionThe city paused data-center development approvals for one year, ending earlier if it adopts new zoning rules.[8][54]
SouthportBrunswick2026.09.10in_effect15 months or earlier adoption of UDO amendments for these usesTown limitsThe city adopted a 15-month pause on new data-center approvals while it develops zoning rules. It ends earlier if the city adopts UDO amendments for these uses.[55][56][57]
AshevilleBuncombe2026.06.23in_effectOne-year pauseThe city adopted a one-year pause on new data-center development under Ordinance 5238.[58]
Black MountainBuncombe2026.05.11ordinance_adoptedPermanent zoning standardsThe town adopted data-processing-center definitions, permitted uses and regulations. A possible moratorium draft was requested for future consideration.[59]
WoodfinBuncombe2026.05.19in_effectThe town's adopted-ordinance index lists Ordinance 2026-04 establishing a temporary pause on new data centers.[60]
Buncombe CountyBuncombe2024.10.15ordinance_adoptedPermanent zoning amendmentThe county board of commissioners approved a zoning text amendment addressing data centers and cryptocurrency mining on October 15, 2024, per the county planning review.[61]
WeavervilleBuncombe2026.04.27ordinance_adoptedPermanent zoning text amendmentTown zoning jurisdictionTown Council classed data centers and crypto mining as noxious uses on April 27, 2026, by a 6-0 vote. Noxious uses need a council-approved conditional district in the I-1 district. This is a permanent zoning rule, not a moratorium.[62][63]
HildebranBurke2026.03.11ordinance_adoptedPermanent zoning standardsThe town adopted conditional zoning standards for data centers and other critical digital infrastructure facilities.[64]
HildebranBurke2026.08.24in_effectTwelve-month term reported by news. The adopted ordinance text was not read.The council adopted a temporary moratorium on development approvals for critical digital infrastructure facilities on August 24 by unanimous vote.[65][66][67]
Camden CountyCamden2026.08.03in_effect2027.01.03Earlier adoption of zoning amendments addressing these usesUnincorporated countyThe county adopted a five-month pause ending January 3, 2027, or earlier adoption of zoning amendments.[15][68][69]
NewportCarteretin_effectAt least one yearTown limits and ETJThe town approved a pause lasting at least one year across its town and extraterritorial jurisdiction.[70][16]
Chatham CountyChatham2026.02.11in_effect2027.02.11Earlier approval of new data-center zoning regulationsUnincorporated countyThe county adopted a twelve-month pause on data-center development approvals, ending earlier if new zoning regulations are approved.[71][1][72]
ApexChatham2026.04.14in_effect2027.04.27Twelve-month pause effective April 28, 2026The town adopted a twelve-month pause effective April 28, 2026. Its official advisory-board page confirms the ongoing moratorium study.[73][74][75]
CaryChatham2026.08.27in_effect18-month moratoriumThe town adopted an eighteen-month pause on data-center development applications.[76][77]
Eastern Band of Cherokee IndiansCherokee2026.05.07permanent_banIndefinite moratoriumTribal lands within Cherokee CountyTribal Council ratified Ordinance No. 158 in open Council on May 7, 2026. It prohibits data centers on EBCI Tribal lands and remains in effect indefinitely.[78][79][80][81]
Cherokee CountyCherokeeproposedThe county did not adopt a data-center moratorium. A draft high-impact land use ordinance that covers data processing facilities went to the planning board, which reviewed it on July 14, 2026.[82][83][17]
Clay CountyClay2026.01.08permanent_banPermanent ordinance, effective on adoptionUnincorporated county outside municipal limits and extraterritorial jurisdictionsOrdinance No. 01.08.2026 prohibits commercial data centers with a peak power demand of 2 megawatts or more in every zoning district of the unincorporated county. It passed 5-0 on January 8, 2026, with no end date.[18][19]
Kings MountainCleveland2026.02.24extended2027.08.24Earlier termination by City Council based on progress or state or federal actionCity planning jurisdictionThe initial pause began February 24, 2026. The city now states a cap of August 24, 2027, with earlier termination possible.[20][84]
Columbus CountyColumbusvote_scheduledProposed 120-day term from adoption, per the draft ordinance in the 2026.10.05 agenda packet (news reports said 90 days)2026.10.05: Public hearing on proposed data-center moratoriumunincorporated areas of Columbus County outside municipal extraterritorial jurisdictions (proposed)Commissioners hold a 2026.10.05 hearing on a proposed 120-day pause on development approvals for data centers in the unincorporated county. The packet revised the term from the 90 days first reported.[10][85][86]
WhitevilleColumbus2026.08.25in_effect2027.08.25Earlier adoption of a zoning ordinance text amendment covering the usesThe city adopted a twelve-month pause on data centers and cryptocurrency mining. It ends August 25, 2027, or when replacement zoning standards are adopted.[9][87]
Cumberland CountyCumberland2026.06.15in_effectStated six-month duration, exact calendar end unconfirmedThe county approved a six-month data-center moratorium. Draft replacement standards were discussed September 15 and remain under review.[21]
Cumberland CountyCumberlandproposed2026.10.20: Joint Planning Board meeting on the proposed data-center ordinanceReplacement data-center zoning standards presented September 15 remain proposed and unadopted. The county lists an October 20 Joint Planning Board meeting and a November public hearing.[21]
FayettevilleCumberlandrejectedCity of FayettevilleOn August 10, 2026, a motion to reconsider a moratorium failed 5-5. The council sent draft data-center rules back to staff for late October.[88][5][89]
Davidson CountyDavidsonrejectedThe proposed temporary moratorium failed on a three-to-three vote on August 24. On September 28 the board passed a four-to-two motion to give staff direction on the moratorium, with no adoption recorded.[22][23][24]
Davie CountyDavie2026.07.06in_effectStated twelve-month duration, exact calendar end unconfirmedThe county approved a one-year pause on data-center construction and development on July 6. The exact end date could not be confirmed.[90]
Durham CountyDurham2026.08.24in_effectStated nine-month duration, exact calendar end unconfirmedThe county approved a nine-month moratorium on accepting and processing applications for new or expanded data centers.[91]
DurhamDurham2026.05.04extended2027.05.03Twelve-month total following June 15 extensionThe city extended its initial pause on June 15, 2026. Its official planning notice states expiration May 3, 2027.[92][5]
CaryDurham2026.08.27in_effectStated eighteen-month duration, exact calendar end unconfirmedCouncil adopted an eighteen-month pause on data-center development approvals. Smaller internal data-processing equipment is exempt.[76][93]
RaleighDurhamvote_scheduledProposed six-month duration, ending earlier if replacement amendments are adopted2026.10.06: Public hearing on proposed data-center moratoriumCity corporate limits and extraterritorial jurisdictionCouncil scheduled an October 6 hearing on a proposed six-month pause for major data-center approvals.[94][95]
Edgecombe CountyEdgecombe2026.08.03in_effectStated two-year duration, exact calendar end unconfirmedCounty zoning jurisdictionThe county adopted a two-year data-center moratorium on August 3. The exact calendar end date remains unconfirmed.[5][96][97][98]
Forsyth CountyForsythrejectedCommissioners declined to advance a proposed six-month pause to a public hearing. The proposal did not create a county moratorium.[99][100]
KingForsyth2026.09.08in_effectSixty-day term stated in the staff report. A twelve-month extension is under review.2026.10.05: Council considers setting a November 2 legislative hearing on a twelve-month extensionCity of King zoning jurisdictionThe council adopted a sixty-day pause on data centers on September 8. On September 28 the planning board recommended a twelve-month extension by a five-to-zero vote.[101][102][103]
Franklin CountyFranklin2026.07.13ordinance_adoptedThe county approved UDO amendment 26-UDO-01 defining data centers and establishing review standards. This is a permanent zoning amendment.[104]
Kings MountainGaston2026.02.24extended2027.08.24Earlier termination by City Council based on progress or state or federal actionCity planning jurisdictionThe initial pause began February 24, 2026. The city now states a cap of August 24, 2027, with earlier termination possible.[20][84]
Gates CountyGates2025.12.17in_effectThe county's planning presentation confirms its adopted data-center moratorium. A proposed replacement amendment would prohibit data centers and still requires a hearing.[26]
Gates CountyGatesproposedThe Planning Board recommends a permanent data-center prohibition. Formal adoption still requires a public hearing and future county board action.[26]
Eastern Band of Cherokee IndiansGraham2026.05.07permanent_banIndefiniteTribal lands in Graham CountyTribal Council ratified Ordinance No. 158 in open Council on May 7, 2026. It prohibits data centers on EBCI Tribal lands and remains in effect indefinitely.[78][79][80][81]
ButnerGranville2026.07.02in_effect2027.01.08Council directed staff to prepare an extension to May 8, 2027, not yet adoptedTown limits and extraterritorial jurisdictionThe town adopted a six-month moratorium, Ordinance 26-07-01, after a July 2, 2026 hearing. It ends January 8, 2027. In September the council asked staff to prepare an extension to May 8, 2027.[29][105][28]
Granville CountyGranvilleproposedGranville County zoning jurisdictionThe county chose zoning rules over a moratorium. Commissioners held a hearing on August 3, 2026, on an amendment that sends data centers through conditional zoning. Final adoption is not confirmed in county records.[27]
CreedmoorGranvilleproposedCity of CreedmoorThe city chose zoning rules over a moratorium. It held an August 4, 2026 hearing on a text amendment that defines data centers and sets standards. The outcome was not readable on the city site.[106][28]
GreensboroGuilford2026.08.18in_effect2027.02.14A 180-day pause covers new data centers with projected electrical demand above 10 megawatts.[107]
Guilford CountyGuilfordproposed2026.10.15: Reported legislative public hearing on the proposed moratoriumunincorporated countyA 180-day data-center moratorium is proposed. A legislative public hearing is reported for October 15.[108][109]
Halifax CountyHalifaxvote_scheduled2026.10.19: Legislative hearing on a proposed data-center moratoriumHalifax County zoning jurisdictionOn September 8, 2026, commissioners voted 5-1 to hold a legislative hearing on a data-center moratorium at their October 19 meeting.[30][25]
Harnett CountyHarnett2026.05.04in_effect2027.05.03Unless otherwise rescinded or extendedunincorporated countyA one-year pause was adopted May 4. The stated expiration is May 3, 2027.[110][111][112]
CantonHaywood2026.02.11in_effect12 months. Exact expiration date unconfirmedA 12-month moratorium pauses new data centers and cryptocurrency mining.[113][2]
ClydeHaywood2026.04.16in_effect12 months from adoption on April 16, 2026. The ordinance states no calendar end dateCorporate limits of the Town of ClydeThe town approved a one-year data-center moratorium.[114][6][115]
Eastern Band of Cherokee IndiansHaywood2026.05.07permanent_banIndefinite moratoriumEastern Band of Cherokee Indians landsTribal Council ratified Ordinance No. 158 in open Council on May 7, 2026. It prohibits data centers on EBCI Tribal lands and remains in effect indefinitely.[78][79][80][81]
HendersonvilleHenderson2026.09.03in_effect2027.09.02Expires at 11:59 p.m. on September 2, 2027, unless earlier ended by councilThe city adopted a one-year pause on data-center building, zoning and special use permits.[31][116][117]
Henderson CountyHenderson2026.07.15ordinance_adoptedCounty land-development jurisdiction outside municipal ETJs, plus jurisdictions requesting county enforcementThe Land Development Code contains permanent standards for cryptocurrency mining operations and data centers.[118][31]
Hertford CountyHertford2024.03.18ordinance_adoptedPermanent development ordinance provisionHeavy Industrial districtThe county's Unified Development Ordinance, effective March 18, 2024, allows a data center only by special use permit in the Heavy Industrial district, with added standards. The provision remains in the ordinance as amended December 1, 2025.[32]
StatesvilleIredell2026.09.14in_effect2027.03.13Or earlier on City Council approval of new regulations or policies for data centersCity of Statesville and its extraterritorial jurisdictionCouncil approved the second reading September 14 on its consent agenda. The ordinance runs from September 14, 2026, to March 13, 2027, and excludes previously approved development.[119][120][121][122]
Jackson CountyJackson2026.08.18in_effectOne year. Exact expiration date unconfirmedMinutes confirm unanimous adoption of a one-year moratorium August 18. The exact expiration and coverage were not stated in the opened minutes.[47]
Eastern Band of Cherokee IndiansJackson2026.05.07permanent_banIndefinite moratoriumEastern Band of Cherokee Indians landsTribal Council ratified Ordinance No. 158 in open Council on May 7, 2026. It prohibits data centers on EBCI Tribal lands and remains in effect indefinitely.[78][79][80][81]
Lee CountyLee2026.04.20ordinance_adoptedThe adopted Unified Development Ordinance contains permanent data-center standards.[123][5]
SanfordLee2026.04.21ordinance_adoptedThe adopted Unified Development Ordinance contains permanent data-center standards.[123][5]
LincolntonLincoln2026.09.03in_effect2027.01.01City of LincolntonCity Council adopted a moratorium on applications for data storage facilities on September 3, 2026, by a 3-1 vote. It ends January 1, 2027.[124][125]
FranklinMacon2026.07.06in_effectExpires automatically twelve months after adoption on July 6, 2026, unless ended earlier or extendedtown planning jurisdictionThe town adopted a one-year data-center moratorium.[126][127][128][129]
Macon CountyMacon2026.08.11ordinance_adoptedThe county amended its high-impact land use ordinance to regulate data centers and server-based facilities.[33][130][131]
HighlandsMacon2026.08.20in_effectTown of Highlands planning jurisdictionTown commissioners approved a temporary data-center moratorium after a public hearing on August 20, 2026. The draft described a 12-month term. The adopted text and end date were not readable on the town site.[34][132]
Hot SpringsMadison2026.07.13in_effect2027.07.13Earlier extension or termination by the Board of AldermenTown of Hot Springs planning and zoning jurisdictionThe town adopted a one-year moratorium on data centers and crypto mining on July 13, 2026. It expires July 13, 2027, unless the board extends or ends it earlier.[133][134]
McDowell CountyMcDowell2026.08.31in_effectSix months. Exact expiration date unconfirmedCommissioners approved a six-month pause on August 31. The exact end date was not stated in readable evidence.[35][135][136]
CharlotteMecklenburg2026.06.08in_effect2026.11.05Earlier City Council approval of new data-center regulations or policies2026.10.12: Public hearing on extension of the current data-center moratoriumcity limits and ETJCharlotte pauses data-center approvals through November 5, 2026, or earlier replacement rules. Council scheduled an October 12 hearing on a proposed extension.[137][7][138][139][140]
Montgomery CountyMontgomeryproposedDraft term: one year from the effective dateCounty land-use and planning jurisdictionA draft one-year moratorium was on the September 15, 2026 commissioners' agenda as a discussion item. It was not adopted. A moratorium needs a public hearing before adoption.[141][142]
Spring HopeNash2026.05.04in_effectOne-year term, exact end date unconfirmedCommissioners unanimously approved data-center resolution 2026-01 on May 4, 2026. The minutes describe a one-year pause.[143][144][145]
Nash CountyNash2026.09.08in_effect2027.06.30Or earlier on approval of new zoning rules for these usesUnincorporated Nash CountyCommissioners adopted a moratorium on September 8, 2026, after a public hearing. It ends June 30, 2027, or earlier when the county adopts zoning rules for these uses.[146][147][12]
NashvilleNash2026.08.04in_effect2027.07.23Or earlier on approval of new zoning regulations for these usesIncorporated areas and planning jurisdiction of the Town of NashvilleTown Council adopted Ordinance 2026-23 on August 4, 2026, after its second public hearing. The ordinance states a term from July 23, 2026, to July 23, 2027.[148][36][149]
BaileyNash2026.05.18in_effect10-month termTown of Bailey and its extraterritorial jurisdictionCommissioners adopted a 10-month data-center moratorium by resolution on May 18, 2026, by a 3-1 vote. On June 15, 2026, they adopted an amended resolution that revised the data-center definition.[150][151][152][149]
Northampton CountyNorthampton2026.05.04in_effect2029.01.04Through January 4, 2029, unless earlier terminated, extended or modified by the boardCounty jurisdictionThe county adopted a 32-month data-center pause on May 4, 2026. It runs through January 4, 2029.[13][145][153][154]
Orange CountyOrange2026.04.21in_effectOne-year term, exact end date unconfirmedCounty minutes confirm unanimous adoption of a one-year data-center moratorium April 21, 2026.[155][156]
Orange CountyOrangeproposed2026.11.04: Planning Board Ordinance Review Committee review of draft data-center standardsCounty planning jurisdictionA planning memo for the October 6, 2026 board meeting sets a schedule for permanent data-center standards, with a hearing expected March 2027.[156]
DurhamOrange2026.05.04extended2027.05.03Twelve-month total following June 15 extensionThe city extended its initial pause on June 15, 2026. Its official planning notice states expiration May 3, 2027.[92][5]
HillsboroughOrange2026.05.27extended2027.05.27Or earlier on approval of new zoning regulationsTown limits, extraterritorial jurisdiction, and future planning areaThe town adopted a 60-day moratorium on May 27, 2026. On June 22, 2026, the board extended it to May 27, 2027, or earlier approval of new zoning rules.[157][158]
Pasquotank CountyPasquotank2026.05.18in_effect2027.05.17Earlier approval of data-center zoning amendmentsUnincorporated county outside municipal extraterritorial jurisdictionsThe county pauses data-center permits until May 17, 2027, or earlier adoption of zoning amendments.[37]
Pasquotank CountyPasquotankproposed2026.10.22: Planning Board meeting on the UDO projectUnincorporated county outside Elizabeth City limits and ETJThe draft UDO proposes prohibiting data centers. County adoption remains required, and the proposed rule may change during review.[38]
Perquimans CountyPerquimansproposedDraft term of one year. The posted draft states September 8, 2026, through September 7, 2027, unless the board ends, extends or modifies it earlier2026.10.05: Public hearing on the data-center moratoriumUnincorporated countyThe county posted a draft one-year data-center pause and set an October 5, 2026 public hearing. No adoption appears in the opened county records.[159][160]
FarmvillePitt2026.08.03in_effectOne-year term, exact end date unconfirmedTown of Farmville and its extraterritorial jurisdictionFarmville adopted a 12-month data-center pause on August 3, 2026, for the town and its extraterritorial jurisdiction.[161][162][163]
Randolph CountyRandolph2026.08.03ordinance_adoptedThe county regulates data-processing facilities through its adopted UDO, amended August 3, 2026. The use requires HI-CD zoning.[39]
Richmond CountyRichmondordinance_adoptedThe current adopted UDO defines data centers and permits the use in its zoning table. The data-center provision adoption date remains unconfirmed.[40]
Rockingham CountyRockinghamproposedThe September 14, 2026 Planning Board agenda lists proposed data-processing facility standards. County adoption remains unconfirmed.[41][164]
Rowan CountyRowan2026.05.04in_effect2027.05.04Earlier termination by majority-vote resolution of the Board of CommissionersCounty zoning jurisdictionThe county adopted a one-year data-center moratorium on May 4, 2026. It expires no later than May 4, 2027, unless the board ends it earlier by resolution.[165][166]
SalisburyRowan2026.06.02ordinance_adoptedCity Council approved data-storage facility zoning amendments June 2, 2026.[42]
Stokes CountyStokesrejectedCommissioners rejected a six-month data-center moratorium in July 2026.[11][167][168]
KingStokes2026.09.08in_effectSixty days from adoption, unless ended earlier or extended by the council2026.10.05: Council considers setting a November 2 hearing on a 12-month extensionCity limits and extraterritorial jurisdictionThe council adopted a 60-day pause on data centers and related uses on September 8, 2026. Staff and the Planning Board recommend a 12-month extension.[101][102]
Surry CountySurry2026.06.01extended2028.07.20All areas subject to Surry County zoning authority and jurisdictionThe county extended its original June 1 pause on July 20, 2026. The published expiration is July 20, 2028.[169]
Mount AirySurry2026.07.16extended60 days from July 16, 2026, plus a 90-day extension approved September 14, 2026Areas subject to city zoning authorityThe city adopted a 60-day data-center pause on July 16, 2026. A city staff report states that a 90-day extension was approved September 14, 2026.[170]
Mount AirySurryproposed2026.10.15: Public hearing on proposed data-center ordinanceThe city scheduled an October 15 hearing on permanent data-center rules that the Planning Board recommends.[171][172]
Swain CountySwain2026.04.21in_effect12-month term, exact calendar expiration not confirmedunincorporated countySwain County adopted a 12-month pause on new data centers in April 2026.[6][173]
Eastern Band of Cherokee IndiansSwain2026.05.07permanent_banIndefiniteLands of the Eastern Band of Cherokee IndiansTribal Council ratified Ordinance No. 158 in open Council on May 7, 2026. It prohibits data centers on EBCI Tribal lands and remains in effect indefinitely.[78][79][80][81]
BrevardTransylvania2026.03.16expired2026.07.02Brevard adopted a temporary pause in March. Its stated July 2, 2026 expiration has passed.[174][175][176][177]
BrevardTransylvania2026.05.18ordinance_adoptedOrdinance 2026-19 established data-center definitions and land-use regulations.[174][175]
WaxhawUnion2026.08.11in_effect2027.08.10Earlier adoption of data-center regulations or termination by the BoardTown of WaxhawThe town adopted a twelve-month data-center pause on August 11, 2026. It ends no later than August 10, 2027.[178]
Union CountyUnionproposedAn August 17 agenda proposed permanent data-center and cryptomining standards. The available official item has no recorded final action.[179]
Indian TrailUnionproposedThe September 15 planning packet proposed data-center definitions and standards under amendment ZT 2026-0095. Council adoption remains unconfirmed.[43]
Vance CountyVance2026.09.14in_effect2026.11.13Or earlier on adoption of data-center zoning amendmentsVance County land use jurisdictionCommissioners adopted a 60-day data-center moratorium on September 14, 2026, by a 5-2 vote. It ends November 13, 2026, or earlier when new data-center zoning rules are adopted.[180][44]
ApexWake2026.04.14in_effect2027.04.27Twelve-month pause effective April 28, 2026The town adopted a twelve-month data-center pause on April 14, 2026, effective April 28. Public reporting states expiration April 27, 2027.[73][74][4][5]
CaryWake2026.08.27in_effect18-month moratoriumIndependent reports confirm an eighteen-month pause adopted August 27, 2026. No exact calendar expiration was stated.[76][77][5]
DurhamWake2026.05.04extended2027.05.03Twelve-month total following June 15 extensionThe city extended its initial pause on June 15, 2026. Its official planning notice states expiration May 3, 2027.[92][5]
Holly SpringsWake2026.06.16in_effectUp to twelve months, exact calendar expiration not confirmedtown limits and ETJThe town approved a pause of up to twelve months on June 16, 2026. Town limits and the ETJ are covered.[181][182][183]
WendellWake2026.04.13in_effect2026.12.31Earlier approval of new zoning regulations for these usesIncorporated areas and planning jurisdictionThe town adopted a data-center pause on April 13, 2026. It runs through December 31, 2026, or until new zoning rules are approved.[5][77][184][185]
RaleighWakevote_scheduledProposed six-month pause2026.10.06: Public hearing and possible council voteRaleigh planning jurisdiction (proposed)The city council holds a 2026.10.06 evening hearing on a proposed six-month pause on development approvals for larger data centers in its planning jurisdiction. Council may vote the same night.[94][186]
Warren CountyWarrenproposedOfficial planning materials describe a proposed moratorium and permanent data-center standards. Adoption following the August 19 hearing remains unconfirmed.[46][45]
BooneWatauga2026.03.23in_effectOne-year term, exact calendar expiration not confirmedtown limitsThe town approved a one-year data-center and cryptocurrency-mining pause on March 23, 2026. Its exact calendar expiration was not stated.[187][188][189]
Watauga CountyWatauga2026.04.21in_effectOne-year termCounty commissioners unanimously passed a one-year moratorium on data centers and crypto mining on April 21, 2026, separate from the Town of Boone's.[3][188][190]
WilsonWilson2026.05.21in_effectTwelve-month term, ending earlier if permanent zoning regulations are adopted. Exact calendar expiration unconfirmedIncorporated areas and planning jurisdiction of the City of WilsonWilson adopted a twelve-month data-center moratorium on May 21, 2026. It pauses new applications and ends earlier upon permanent zoning regulations.[191][192]
Yadkin CountyYadkin2026.08.17in_effectTwo-year term, exact calendar expiration not confirmedunincorporated countyIndependent reporting confirms a two-year pause in unincorporated areas. An exact calendar expiration was not stated.[193][194]
JonesvilleYadkinproposedThe town's September 28 meeting notice included a resolution to schedule a hearing on a temporary data-center moratorium. The outcome remains unconfirmed.[195]

Cite this dataset

FOUND, "Where North Carolina has paused data centers", lotsfound.com, 2026. Data from public sources listed below. Licensed CC BY 4.0.

Free to reuse with attribution to FOUND and a link to this page (CC BY 4.0).

Sources

  1. Chatham County public record
  2. Canton public record
  3. Watauga County public record
  4. Apex public record
  5. Wendell public record
  6. Swain County public record
  7. Charlotte public record
  8. Boiling Spring Lakes public record
  9. Whiteville public record
  10. Columbus County public record
  11. Stokes County public record
  12. Nash County public record
  13. Northampton County public record
  14. Beaufort County public record
  15. Camden County public record
  16. Newport public record
  17. Cherokee County public record
  18. Clay County public record
  19. Clay County public record
  20. Kings Mountain public record
  21. Cumberland County public record
  22. Davidson County public record
  23. Davidson County public record
  24. Davidson County public record
  25. Halifax County public record
  26. Gates County public record
  27. Granville County public record
  28. Creedmoor public record
  29. Butner public record
  30. Halifax County public record
  31. Henderson County public record
  32. Hertford County public record
  33. Macon County public record
  34. Highlands public record
  35. McDowell County public record
  36. Nashville public record
  37. Pasquotank County public record
  38. Pasquotank County public record
  39. Randolph County public record
  40. Richmond County public record
  41. Rockingham County public record
  42. Salisbury public record
  43. Indian Trail public record
  44. Vance County public record
  45. Warren County public record
  46. Warren County public record
  47. Jackson County public record
  48. Alamance County public record
  49. Alamance County public record
  50. Sparta public record
  51. Beaufort County public record
  52. Elizabethtown public record
  53. Elizabethtown public record
  54. Boiling Spring Lakes public record
  55. Southport public record
  56. Southport public record
  57. Southport public record
  58. Asheville public record
  59. Black Mountain public record
  60. Woodfin public record
  61. Buncombe County public record
  62. Weaverville public record
  63. Weaverville public record
  64. Hildebran public record
  65. Hildebran public record
  66. Hildebran public record
  67. Hildebran public record
  68. Camden County public record
  69. Camden County public record
  70. Newport public record
  71. Chatham County public record
  72. Chatham County public record
  73. Apex public record
  74. Apex public record
  75. Apex public record
  76. Cary public record
  77. Wendell public record
  78. Eastern Band of Cherokee Indians public record
  79. Eastern Band of Cherokee Indians public record
  80. Eastern Band of Cherokee Indians public record
  81. Eastern Band of Cherokee Indians public record
  82. Cherokee County public record
  83. Cherokee County public record
  84. Kings Mountain public record
  85. Columbus County public record
  86. Columbus County public record
  87. Whiteville public record
  88. Fayetteville public record
  89. Fayetteville public record
  90. Davie County public record
  91. Durham County public record
  92. Durham public record
  93. Cary public record
  94. Raleigh public record
  95. Raleigh public record
  96. Edgecombe County public record
  97. Edgecombe County public record
  98. Edgecombe County public record
  99. Forsyth County public record
  100. Forsyth County public record
  101. King public record
  102. King public record
  103. King public record
  104. Franklin County public record
  105. Butner public record
  106. Creedmoor public record
  107. Greensboro public record
  108. Guilford County public record
  109. Guilford County public record
  110. Harnett County public record
  111. Harnett County public record
  112. Harnett County public record
  113. Canton public record
  114. Clyde public record
  115. Clyde public record
  116. Hendersonville public record
  117. Hendersonville public record
  118. Henderson County public record
  119. Statesville public record
  120. Statesville public record
  121. Statesville public record
  122. Statesville public record
  123. Sanford public record
  124. Lincolnton public record
  125. Lincolnton public record
  126. Franklin public record
  127. Franklin public record
  128. Franklin public record
  129. Franklin public record
  130. Macon County public record
  131. Macon County public record
  132. Highlands public record
  133. Hot Springs public record
  134. Hot Springs public record
  135. McDowell County public record
  136. McDowell County public record
  137. Charlotte public record
  138. Charlotte public record
  139. Charlotte public record
  140. Charlotte public record
  141. Montgomery County public record
  142. Montgomery County public record
  143. Spring Hope public record
  144. Spring Hope public record
  145. Northampton County public record
  146. Nash County public record
  147. Nash County public record
  148. Nashville public record
  149. Bailey public record
  150. Bailey public record
  151. Bailey public record
  152. Bailey public record
  153. Northampton County public record
  154. Northampton County public record
  155. Orange County public record
  156. Orange County public record
  157. Hillsborough public record
  158. Hillsborough public record
  159. Perquimans County public record
  160. Perquimans County public record
  161. Farmville public record
  162. Farmville public record
  163. Farmville public record
  164. Rockingham County public record
  165. Rowan County public record
  166. Rowan County public record
  167. Stokes County public record
  168. Stokes County public record
  169. Surry County public record
  170. Mount Airy public record
  171. Mount Airy public record
  172. Mount Airy public record
  173. Swain County public record
  174. Brevard public record
  175. Brevard public record
  176. Brevard public record
  177. Brevard public record
  178. Waxhaw public record
  179. Union County public record
  180. Vance County public record
  181. Holly Springs public record
  182. Holly Springs public record
  183. Holly Springs public record
  184. Wendell public record
  185. Wendell public record
  186. Raleigh public record
  187. Boone public record
  188. Watauga County public record
  189. Boone public record
  190. Watauga County public record
  191. Wilson public record
  192. Wilson public record
  193. Yadkin County public record
  194. Yadkin County public record
  195. Jonesville public record