Demolition permit and asbestos survey before a teardown

Before you tear down a house, have an accredited inspector survey it for asbestos, end utility service, and get the local demolition permit. When the federal asbestos rule applies, the state program needs written notice at least 10 working days before demolition starts.

Start an infill lot search

Quick summary: This guide explains the asbestos survey, the state asbestos notice, the utility disconnects, and the local demolition permit that come before a teardown. It is for infill builders and investors who plan to replace an existing house. The key takeaway: survey for asbestos first, because the survey decides which state rules apply, and the local permit does not replace them.

What a teardown needs before demolition

A teardown needs an asbestos survey, utility disconnects, and a local demolition permit before any wall comes down. State law requires a permit for the demolition of any building or structure. The local inspections department issues it.

The asbestos rules come from a separate program. The state program says that any required local permit is separate from its own notice and permit. A local permit alone does not meet the state requirements. Durham’s demolition application makes the applicant acknowledge this in writing.

The asbestos survey

An asbestos survey is an inspection that finds the presence, type, location, and amount of asbestos in a building. The state program says an accredited asbestos professional must inspect a building before any demolition or renovation begins. State law requires accreditation for anyone who performs asbestos management work, with a separate category for inspectors.

The survey matters because older building materials can hold asbestos. The state’s guidance names examples such as vinyl flooring, joint compound, plaster, ceiling tiles, and cement siding and roofing. It defines asbestos-containing material as material with more than 1 percent asbestos.

Which rule applies to a house

The federal asbestos rule covers most buildings but excludes small residential buildings. Its definition of a facility excludes residential buildings having four or fewer dwelling units. Durham’s demolition permit application notes that the rule still applies when a residence is demolished for commercial, institutional, or industrial purposes.

The state program recommends an inspection for every building, including single-family homes and buildings with four or fewer units. The survey tells you whether asbestos is present, what precautions to take, and whether a state removal permit is needed.

The short version: Survey every house before a teardown. The survey decides whether the federal notice, a state removal permit, and accredited removal workers apply.

The state notice and the removal permit

The state notice is a written notice to the state asbestos program before demolition. North Carolina adopts the federal rule and sends its filings to the state, as state asbestos rules direct. Local programs in Mecklenburg, Buncombe, and Forsyth counties have their own requirements, and the state requirements still apply there.

The notice period. For a demolition the federal rule covers, the notice goes in at least 10 working days before demolition begins. The notice is required even when the survey finds no asbestos.

The removal permit. A state removal permit is required to remove more than 35 cubic feet, 160 square feet, or 260 linear feet of regulated asbestos-containing material. The application must reach the program at least 10 working days before removal starts.

The order. Accredited workers remove the regulated material before demolition begins. The same state guidance warns that pre-1978 housing can add lead-based paint requirements.

Utility disconnects

Every utility line to the house must be ended and made safe before demolition. Durham’s demolition permit application shows the detail a town can ask for:

  • A plot plan that shows every existing utility at the address.
  • Removal of the water meter by the city before demolition.
  • A sewer cleanout at the right of way that is capped and located if the work disturbs it.
  • An infrastructure inspection request 48 hours before and after the demolition.

Call the electric and gas providers to end service and pull the meters. Before any demolition, state law requires notice to the one-call Notification Center at least three full working days ahead. The same statute gives each utility a reasonable time to remove or protect its lines.

On a well or septic system, the county may need to approve first. Raleigh requires approval from Wake County Environmental Services before you apply for a demolition permit on a lot with a private well or septic.

The local demolition permit

The local demolition permit is the inspections department’s approval to remove the building. Each town sets its own application. Raleigh asks for a site plan or survey that identifies the structures to remove. Durham’s applicant agrees that the site must be cleared of all debris, including the foundation and footings, and graded for drainage.

Historic districts. A house in a local historic district or a landmark needs a certificate of appropriateness before demolition. State law lets the commission delay the certificate’s effective date for up to 365 days from approval.

The existing house’s setback. Demolition can change where the new house may sit. Where Raleigh’s infill rules apply, a new house may sit within 10 percent of the old house’s front setback. An official survey must show that the old house stood there within the last 365 days. Have a surveyor locate the house before it comes down.

Take action: Send the lot’s address before you sign, and get the zoning, historic district, and utility questions in order. Start with Can the house you want fit on this lot?

The order of steps

You run a teardown in seven steps, with the questions that can stop the project first.

  1. Confirm the zoning, any historic district, and the lot standards for the new house. See What is infill development.
  2. Have a licensed land surveyor locate the existing house and utilities.
  3. Hire an accredited asbestos inspector to survey the house.
  4. If the survey finds regulated material above the threshold, apply for the state removal permit and have accredited workers remove it.
  5. File the state demolition notice where the federal rule applies.
  6. End utility service, remove the meters, and notify the Notification Center.
  7. Get the local demolition permit, demolish, clear the site, and pass the inspections.

An asbestos survey looks at building materials. It does not check the ground for contamination from past uses. That question belongs to a Phase 1 environmental site assessment: what it is and when you need one.

Who answers the question

The local inspections department answers the permit question, and other parties answer the rest.

  • An accredited asbestos inspector surveys the house.
  • The state asbestos program takes the notice and issues removal permits.
  • The utilities end service and remove meters.
  • The preservation commission reviews demolition in a historic district.
  • A licensed land surveyor locates the house and the lot lines.

The public record shows the zoning, any historic district, and the year the house was built. It does not show what is inside the walls. We read the record in a fixed order and hand you the open questions. For a lot you plan to split after demolition, see Lot split: can you split your lot.

Key recap

  • State law requires a local permit for the demolition of any building or structure.
  • The state program says an accredited professional must inspect a building for asbestos before demolition.
  • The federal rule excludes residential buildings with four or fewer units, but the state recommends a survey for every house.
  • Where the federal rule applies, the state notice goes in at least 10 working days before demolition, even with no asbestos found.
  • Utility disconnects, the Notification Center notice, and any historic district review come before the wrecking.

Questions

Do I need an asbestos survey to demolish a house in North Carolina?

The state program says an accredited asbestos professional must inspect a building before demolition, and it recommends a survey for every house. The federal rule excludes residential buildings with four or fewer units in most cases. Ask the state program which rule applies to your project.

How long before demolition must I notify the state?

Where the federal rule applies, the notice goes in at least 10 working days before demolition begins. A state removal permit for regulated asbestos also needs 10 working days.

Does the local demolition permit cover the asbestos rules?

No. The state program says a local permit is separate and does not meet the state notice or permit requirements.

Who removes asbestos before a teardown?

North Carolina accredited asbestos workers and supervisors remove regulated material. The removal comes before demolition starts.